I am excited about all 2015 has to offer Birdville ISD. With the passage of the bond referendum in November 2014, there will be a lot of work taking place across the District in the next 36-48 months. The rebuilding of The Academy at West Birdville Elementary, Birdville Elementary and North Richland Middle School, updating outdated classroom technology and secondary science labs, renovating campuses and adding additional safety measures will require a great deal of coordination. Staff members are in the process of developing a master schedule to assist the District in making certain each component of the voter-approved bond is completed as committed to.

Beginning the work as promised …

  • In December, BISD’s Board of Trustees approved HKS, Inc. as the architectural firm to design the new building for The Academy at West Birdville Elementary. The design work began in December 2014 in order to complete construction of this campus in time for opening in the fall of 2016.
  • During January and February, the Board will interview architectural firms for the opportunity of designing and replacing Birdville Elementary and North Richland Middle School. Once a decision is made by the Board, it will be shared through the District’s normal communications channels.

In the coming weeks, BISD will be adding a bond update page to their website. This page will provide details on all aspects of the 2014 Bond.

It is the District’s goal to preserve the community’s valued trust by maintaining transparency throughout the entire process.

[tweetthis]It is the District’s goal to preserve the community’s valued trust by maintaining transparency throughout the entire process.[/tweetthis]

Board approves architectural firm to design The Academy at West Birdville

At their regular December meeting, BISD’s Board of Trustees authorized the selection of HKS, Inc. as the architectural firm to design the replacement school for The Academy at West Birdville Elementary. In order to complete construction of the project in time for opening in the fall of 2016, the design work would begin in December 2014.

The rebuilding of The Academy at West Birdville Elementary is part of the bond referendum approved by voters on Nov. 4, 2014.

BISD voters approve 2014 bond: Now what?

SchoolhouseColorNow that the bond has passed, the Board and Administration have begun the complex process of developing a timeline for completing all aspects of the projects included in the bond referendum. This timeline will be published on our website as soon as it has been completed. Progress reports will also be posted regularly online.